  • GTA Refurbishment - Open Visits

    This coming Thursday and Friday - we'll be available to guide colleagues around the newly refurbished rooms in 3E and 6E. Just drop in to see us! Thursday 14 - 14:00 to 16:00 Meet at 3E Foyer Meet at 6E...

  • GTA Room Rebuilds - Summer 2017

    There are a few rebuilds of rooms going on over this summer..... Namely 3E, 6E and 4E3.38 (left over from last year!). As you can see - progress is good......   More updates over the summer as we make progress!...

  • Summer Refurbs - Update Sept 2016

    We're coming towards the end of the summer break, and many of the rooms are looking much better than they originally were. Some of the biggest changes have been in 1E, 4E and in 3WN. The extent of the work...

  • Summer Upgrades

    This summer, we are rebuilding many of the teaching spaces. Full rebuilds (Furniture, Decoration, Equipment): 1E 2E (but not 3.1) 3WN 4E (not 3.38) Equipment refresh & Decoration: 5W Council Chamber Equipment Refresh 4W 6W 1E3.6, 4E2.56 and 4E3.5 will...

  • 8W Visit Day

    Now that the rebuild process in 8W is complete, we would like to invite everyone to come and visit the rooms to see the extent of the refurbishment, and look over the new technology. The visits will be held on:...

  • 8W Project Update - 2 June 2015

    TheĀ  8W refurbishment continues at some pace. We should be having Level 2 rooms handed back to us late on Friday evening. There are some changes in the rooms: All the rooms will be fully HD and Widescreen. All the...

  • 8W Refurbishment Update - Mid Week 1

    The summer refurbishment project being undertaken on 8W GTA rooms is well underway. Most of the rooms have been stripped out, and are underway with first-fix for the AV equipment, and also with the decoration. The refurbishment will replace many...