This week at BaleHaus at Bath
Posted by Katharine Beadle in BaleHaus build August 11th, 2009Work started again on site yesterday with the electricians coming to lay cabling for power and lighting in the house, which will be mainly hidden under the raised floor. Over the previous couple of work days the joints between the panels have continued to be filled to make airtight seals and the cladding should be applied this and next week.
Merl is finishing the render on the two panels that came from the structures lab as they have now cured for the necessary 14 days. The windows are due next, but because of the scaffolding still being in place these will be inserted from the interior of the building, so the webcam will not show much of this taking place, but there will be photos on the website.