4 East South: Project Update

Posted in: 4 East South

The project has made good progress during December despite a halt in construction over the Christmas period and the recent bad weather conditions:

  • Screeding (levelled concrete flooring) has been completed on level 4.
  • The underfloor heating system has been installed.
  • Installation of paving slabs on the West core roof has been completed.
  • Over 90% of the building’s windows have been installed.
  • East core has been fully insulated.
  • Installation of radiators has begun on Levels 2 and 3 in the West core.
South elevation
South elevation
Internal
Internal progress

Health & Safety

There have been no injuries or accidents on site.

The site has achieved a 98% score in the recent health and safety compliance audit. The team has never scored lower than 97%.

Did you know...?

To date over 170 tons of reinforced steel has been used in the structure, the equivalent weight of a fully grown Blue Whale.

Posted in: 4 East South