Impact of campus investment building projects

Keeping you updated on our current campus building projects

Posts By: Sam Bradley

The Milner Centre for Evolution Project update

  , ,

📥  Milner Centre

Welcome to the third monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution project. Our site manager, Firhan Rudorf-Saeed is on site throughout the working day, and should be the first point of contact for any issues.

They are currently holding weekly meetings with the users of Building 4SA, and attend the monthly University contractors meeting with a view to keeping staff and students informed of their works and to give notice of any potential disruption.

The first stage of the groundworks is nearly complete. They are at the closing stages of excavating the ground to lower levels to install foundations and drainage up to 3m in depth. There will still be some element of noisy works, as the works involving the removal of rock is still ongoing. The noise and vibration is intermittent throughout the working day, and will take them into the end of April/beginning of May. The removal of excavated material from site by haulage lorries is now approximately 85% complete. Road conditions are constantly being monitored, and a road sweeper is being utilised as and when required.

Both the new water connection to Building 4SA and the works to excavate an electricity trench from site to the substation opposite the car park have now been completed. There is no further work planned in the immediate future which will affect the road outside our site compound.

Moving forward, the ground floor slab will be poured in two visits with the use of concrete pumps. The second week of May will see steel arrive on site, and the works involving the steel erection will take us up to the end of May. The steel will be erected with the use of mobile cranes and also mobile elevating working platforms which, unfortunately, do emit a loud beep when in operation.

As always, we appreciate your patience and understanding whilst the construction phase is ongoing.

Current site

Milner Centre site 1 Milner Centre site 2 Milner Chart

 

Polden project update

  , ,

📥  Polden

Welcome to the third monthly update aimed at keeping you up to speed on the new Polden Student Accommodation project.

Our Project Manager Steve Phillips is on site throughout the working day, and should be the first point of contact for any issues. We are working closely with the university Estate and Accommodation staff and attend the monthly university contractors meeting with a view to keeping staff and students informed of our works and to give notice of any potential disruption.

The builders have used the first week of the university Easter break to install their site office and welfare set up within the West Car Park. Power, plumbing and IT are currently being installed to the office to allow our full site team to be based on the project within the next two weeks.

With regard to our site works, they are still in the process of excavating the ground to install foundations and drainage up to 4m in depth from existing ground levels. Unfortunately the removal of rock is still ongoing. The noise and vibration is intermittent throughout the working day and will take us into mid-June.

Foundations are being dug and filled with reinforced cages prior to pouring with concrete to the Eastern side of the site.  This involves several lorry loads of concrete to be delivered to the site on a daily basis.  Wall reinforcement can now be seen coming out of the ground which will form the reinforced walls and columns in the coming weeks. Road conditions are constantly being monitored, and a road sweeper is being utilised as and when required.

Drainage and gas pipes are currently being drilled beneath the West Car Park which will provide connections for the Polden development. We are using Horizontal Directional Drilling below ground to reduce the disruption to the users of the car park. A hole is required at the end of the drain and gas route within the car park to 10West to connect onto but we will continue to liaise with security to minimise the disruption to the car park users.

Live electric cables are in the process of being exposed to allow them to be moved into the road adjacent 7W and 9W in the next week.

Within the next month, we will be erecting a tower crane which will then assist with the construction of the concrete frame which is due to start early May 2017.

As always, we appreciate your patience and understanding whilst the construction phase is ongoing.

Current site

Polden site 2 300x182 Polden site 300x182 Polden chart