Impact of campus investment building projects

Keeping you updated on our current campus building projects

Topic: Uncategorized

Polden development update

  , ,

📥  Polden, Uncategorized

Welcome to the sixth monthly update aimed at keeping you up to speed on the new Polden Student Accommodation project.

June was another busy month for us on the project and as you will know if you have seen the site, this month has seen the building rise out of the ground.

Foundations are now complete to all areas of the building. Our groundworkers are concentrating on digging out and installing drainage beneath the building to allow the ground floor slab to be cast adjacent to 7W and 9W. The excavations against the retaining walls are also now being filled to allow external drainage to link the building into the existing University drainage system.

The concrete structure is progressing at great speed, and we are working on forming the level 2 floor slab to the corner nearest the West Car Park entrance.

We continue to pour concrete every day, forming columns and walls every evening to allow the concrete to cure during the cooler evenings. This allows us to strike the shutters on columns the following morning and prepare the next column to be cast the same afternoon, a method which has allowed the frame to progress quickly.

As always, we appreciate your patience and understanding while the construction phase is ongoing, and we continue to work closely with the Department of Estates, AHS, and Security teams to minimise disruption as much as possible.

Below are a few photos of progress taken from our tower cranes.  What a great view they have 40m above the ground!

Current site (from above)

 

The Milner Centre for Evolution Project update

📥  Uncategorized

Welcome to the monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution project.

The site manager, Firhan Rudorf-Saeed is on site throughout the working day, and should be the first point of contact for any issues. The contractors are currently holding weekly meetings with the users of Building 4SA, and attend the monthly University contractors meeting with a view to keeping staff and students informed of our works and to give notice of any potential disruption.

The first stage of the ground works is nearly complete. They are at the closing stages of excavating the ground to lower levels to install foundations and drainage up to 3m in depth. There will still be some element of noisy works, as the works involving the removal of rock is still ongoing. The noise and vibration is intermittent throughout the working day, and will take us into the beginning of May. The excavated material being removed from site by haulage lorries is now approximately 90% complete while road conditions are constantly being monitored, and a road sweeper is being utilised as and when required.

Both the new water connection to Building 4SA and the works to excavate an electricity trench from site to the substation opposite the car park have now been completed. There is no further work planned in the immediate future which will affect the road outside our site compound.

The ground floor slab has now been poured with the use of concrete pumps. This was a key milestone and allows the next phase of building works to commence – which will see steel arrive on site the 2nd week of May, and the works involving the steel erection will take us up to the end of May. The steel will be erected with the use of mobile cranes, and also mobile elevating working platforms, which, unfortunately do emit a noisy beep when in operation.

As always, we appreciate your patience and understanding whilst the construction phase is ongoing.

NEW milner chart

Current site

Milner 2 MAY Milner 1 MAY