Temporary closure of footpath from West car park to Medical Centre

  

📥  10 West

As part of the 10W project, new gas and data services need to be run from car park D (South of 2 South building) to the new 10W building.

The route involves excavating and laying new services along the footpath that connects the West car park to the Medical Centre, along the South edge of the lacrosse pitch and through car park D.

The works are expected to last for 8 to 9 weeks, starting on Monday 22 June from 10W progressing towards car park D.

  • The footpath that connects the West car park to the Medical Centre (highlighted in green on the map) will be closed for a 3 to 4 week period from this date.
  • The public footpath (highlighted in blue on the map) will remain open for the duration of the works.
  • An alternative route is available by joining the public footpath nearer to Quarry Road at the far end of the West car park (highlighted in magenta on the map).

10W-FOOTPATH-CLOSURE
Further footpath and parking closures may be required as the works progress. We will keep you informed on these pages.

 

1 West Phase 3: Project Update June 2015

📥  1West

Midas Construction Limited continue apace with the reconstruction and fit out.

Installation of the ductwork for ventilation and infrastructure for the electrical services is currently underway.

Works to replace the existing roof with a high performance insulated felt roof have started and will continue over the next seven weeks.

Internal partitioning is due to start soon to provide bespoke office, laboratory and general teaching spaces.

Replacement windows are due on site in early June and scaffolding will start to be struck later in June.

Works to refurbish the existing staircase will also be starting in the next month.

Level 5 roof deck

Level 5 roof deck

Level 2 ductwork

Level 2 ductwork

Potential disturbance

1-West-Capture-2
Noise from the works will be unavoidable, however we hope the traffic light system above will assist.  It is not anticipated that the construction activity will create any more noise than the current ambient noise levels with the exception of the roof decking. Please also note that the dates above are a guide and likely to change as a result of unforeseen changes and site issues.

We do not anticipate any major interface issues with the current use of 1West, Library and 3West however there will be times when works at the junctions with these buildings will require alterations and additional hoarding to allow the tie in to be completed. These will be timetabled and managed in conjunction with the University Estates team. Interface works will be segregated at all times ensuring that the safety of the building user is paramount at all times.

Scaffold and temporary roof

The building is currently enclosed in a scaffold and temporary roof structure to allow the construction works to continue in the dry whilst the roof and windows have been removed. As works proceed these will be progressively removed to expose the new building. The site will be accessed from the level 1 underdeck to minimise contractor interaction with the student population. Site offices are in Brendon Court car park.

Safety will always be paramount to all our operations on site.

Pedestrian movement at site entrance

Site delivery numbers will now increase with the refurbishment of the now empty building shell, all vehicle movements will be strictly managed by Midas traffic marshal and by timing of deliveries around peak pedestrian movements times. Please take direction as required at site entrance gates from Traffic Marshals for your own safety.

General queries should be issued to estates-helpdesk@bath.ac.uk.

Please also see the campus investments webpages.

 

10 West: Project Update - June 2015

📥  10 West

Progress to date

The project is on program and continues to benefit from the good weather conditions:

  • The construction of level 3 has been completed, level 4 is also making good progress.
  • The erection of the steel frame to the west block and atrium is now completed.
  • The facades are now commencing which will allow the internal trades to start work in the near future.
  • The insitu reinforced concrete feature atrium staircase is now in progress.

Ongoing reviews continue with the final users of the building, the Department of Psychology and the Office of Policy and Planning, refining detailed requirements and furniture procurement.

Health & Safety

Extra measures and precautions remain in place around the site when construction vehicles leave and are being monitored to ensure safety. These include measures such as banksmen who are helping vehicles to safely leave the site.

To date there have been no injuries or accidents, the team continue to achieve exemplary levels of safety.

Noise

The noise levels will continue to the same level as they have been in the previous month.

Did you know?...

This project is one of the projects being showcased by the Institute of Civil Engineers as a major project contributing to the local infrastructure, economy and employment.

General queries can be addressed to Estates Helpdesk

Please also see Campus investments webpages and Estates webpages

IMG_1086

10 West progress to date

 

4 East South: Project Update - June 2015

📥  4 East South

Main build

The first sets of precast concrete planks have started on the west core of the building. The preparation of the east side has been completed and the planks will be arriving in the next couple of weeks.

Two cranes are now in use to assist in the increased number of deliveries.

Wheel washers and banksmen are in constant use at the site entrance and all construction vehicles are having their wheels washed down before leaving the site.

Figure 1 Preparation for East Core Walls

Figure 1 Preparation for East Core Walls

Energy Centre

The Energy Centre is complete and fully energised. This building will be handed over to the University in the next few weeks.

Health & Safety

There have been zero accidents on site and the project received 100% score in the safety audit.

There are ongoing reviews to optimise safe construction methods and improve risk management.

Environmental

99.9% of site waste has been diverted from land fill to date. Discussions and research are continuing to use more environmentally friendly construction materials.

Did you know?

Students from the Department of Architecture and Civil Engineering have visited site and future visits are being arranged.

Faculty of Civil Engineering and Architecture Visit

Faculty of Civil Engineering and Architecture Visit

General queries can be addressed to the Estates Helpdesk

Please also see Campus investments webpages and Estates webpages

 

1 West Phase 3: Project Update May 2015

  

📥  1West

Midas Construction Limited is working on Phase 3 of the 1 West refurbishment with the project due to complete in August 2015.

Potential disturbance

1 west forecasts

 

Noise from the works will be unavoidable, however we hope the traffic light system above will assist.  It is not anticipated that the construction activity will create any more noise than the current ambient noise levels with the exception of the roof decking. Please also note that the dates above are a guide and likely to change as a result of unforeseen changes and site issues.

We do not anticipate any major interface issues with the current use of 1West, Library and 3West however there will be times when works at the junctions with these buildings will require alterations and additional hoarding to allow the tie in to be completed. These will be timetabled and managed in conjunction with the University Estates team. Interface works will be segregated at all times ensuring that the safety of the building user is paramount at all times.

1 West May 2015

1West Phase 3 as viewed from the Parade

Scaffold and temporary roof

As can be seen the building is currently enclosed in a scaffold and temporary roof structure to allow the construction works to continue in the dry whilst the roof and windows have been removed. As works proceed these will be progressively removed to expose the new building. The site will be accessed from the level 1 underdeck to minimise contractor interaction with the student population. Site offices are in Brendon Court car park.

Safety will always be paramount to all our operations on site.

Pedestrian movement at site entrance

Site delivery numbers will now increase with the refurbishment of the now empty building shell, all vehicle movements will be strictly managed by Midas traffic marshal and by timing of deliveries around peak pedestrian movements times. Please take direction as required at site entrance gates from Traffic Marshals for your own safety.

General queries should be issued to estates-helpdesk@bath.ac.uk.

Please also see the campus investments webpages.

 

10 West: Project Newsletter - May 2015

  , ,

📥  10 West

Progress to date

The project is on program and is benefiting from the good weather conditions:

  • Works on the underdeck and water main connections have been completed ahead of schedule.
  • The construction of level 1 has been completed, level 2 is also making good progress.
  • The emergence of level 3 lift shafts, staircase columns and the atrium are now visible.
  • The internal walls are making good progress.
  • The erection of the steel frame to the west block and atrium will commence in the next 2 weeks.

Ongoing reviews are underway with the final users of the building, the Department of Psychology and the Office of Policy and Planning, to refine detailed requirements and furniture procurement.

10W-may-550

Health & Safety

  • Extra measures and precautions remain in place around the site when construction vehicles leave and are being monitored to ensure safety. These include measures such as banksmen who are helping vehicles to safely leave the site.
  • To date there have been no injuries or accidents, the team are achieving exemplary levels of safety.

Noise

  • The noise levels will continue to the same level as they have been in the previous month.

Did you know?...

...that the first floor concrete slab weighs approximately the same weight as a fully laden A380 Jumbo Jet. Each floor slab will weigh a similar amount, and there are 5-6 floors.

General queries can be addressed to estates-helpdesk@bath.ac.uk

Please also see Campus investment webpages and Estates webpages

 

4 East South: Project Newsletter - May 2015

  , ,

📥  4 East South

Progress to date

Main build

Work has progressed well over the past month and the team has taken advantage of the good weather.

  • Vertical elements such as columns and core walls have been completed on the West end of the building. Work to the East end of the building is also progressing well.
  • The concrete beams that will support concrete planks will be installed this month, this will form the second floor.
  • Detailed reviews have taken place to fine tune the logistics of the concrete plank installation. The concrete planks are manufactured off site, which allows for quick installation on site. These materials are being delivered on site after the May Bank Holiday.
  • Design workshops continue to take place on a regular basis to discuss the internal and external elements of the building and how we can best achieve the many interfaces between finishes.
  • A new water main has been installed to replace part of the old main.
4ES-may-550

Progress in the coming period

  • Installation of the second floor will be completed in mid May.
  • Construction of the third floor will be in progress by the end of May.
  • Noise will continue at the same level as the past month.

Local sourcing

  • 80% of all staff on site live locally.
  • Bouygues UK are actively sourcing local companies to use for the works.

Health & Safety

  • Zero injury accidents.
  • Visits from senior management continue to ensure the highest standards are met.

General queries can be addressed to estates-helpdesk@bath.ac.uk

Please also see Campus investments webpages and Estates webpages

 

4 East South: Project Newsletter - April 2015

  , ,

📥  4 East South

Progress to date

Main build

Despite minor set backs due to high winds and bad weather the project is on schedule.

  • The final installment of ground floor slabs is complete.
  • Installation of the building frame and columns has started and is making good progress.
  • Wheel washers are in constant use at the site entrance. Construction vehicles are having wheels washed down before leaving the site in order to protect Convocation Avenue.
4-East-South-Apr15-1

 

Energy Centre

  • The Energy Centre structure is complete, water tight and is now fully energised.
  • The existing Energy Centre is gradually being disconnected and all transfers are underway.
  • HV and LV power is live and under a University permit to work.

Progress in the coming period

  • Following completion of the ground floor slabs, construction of the first floor will commence.
  • Installation of a tarmac band around the site will commence to allow safe access to site.
4-East-South-Apr15-2

 

Health & Safety

  • Zero injury accidents.
  • 100% score in safety audit.
  • Ongoing reviews to optimise safe construction methods and improve risk management

Environmental

  • 99.9% of site waste to date diverted from land fill.
  • Bristol & West Archaeology have been in attendance during excavation works but to date, nothing of archaeological value has been identified.
  • Continued discussions and research to use more environmentally friendly construction materials

General queries can be addressed to estates-helpdesk@bath.ac.uk

Please also see Campus investments webpages and Estates webpages

 

10 West: Project Newsletter - April 2015

  , ,

📥  10 West

Progress to date

The project is making excellent progress despite the high wind and bad weather experienced in March.

Extra measures and precautions have been introduced when construction vehicles leave the site, such as banksmen that are helping vehicles to safely leave the site.

  • The construction of level 0 has been completed, Vinci will commence the instalment of internal walls and will commence level 1. This will include the instalment of approximately 250 tonnes of concrete during April. There will be periodic times of high noise as the concrete works are completed.
10-west-Apr15
  • The construction and installation of the drainage system is nearing completion.
  • The foul drainage system has been completed on schedule.
  • A gate is required and will be opened shortly adjacent to the West car park, this is to allow access for an additional crane during May. This will result in a temporary reduction of 8 parking bays from West car park for a period of one month.

General queries can be addressed to estates-helpdesk@bath.ac.uk

Please also see Campus investment webpages  and Estates webpages