  • 10 West: Project update

    Progress to date We are pleased to report the project is still on schedule The concrete frame is now completed together with the atrium stairs which has allowed the crane to be removed from site. As can be seen from...

  • 4 East South: Project update - August 2015

    Progress to date The project is going well, and this month we have made good progress. The reinforced concrete frame up to Level 4 on the West wing, and level 3 on the East has been completed. The West wing...

  • 10 West: Project update - August 2015

    Progress to Date Despite recent wet weather conditions, the project is still on schedule. Construction of level 5 has been completed; work on level 6 is now underway and good progress is being made Both north and south concrete stairs...

  • 1 West Phase 3: Project Update July 2015

    Works to 1 West Phase 3 are moving along at a rapid pace and evidence of the new building is starting to emerge from the scaffold shroud that has been in place for the last few months. Externally 50% of...

  • 4 East South: Project update - July 2015

    Progress to date Main build The concrete structure for level 1-2 has been completed with level 3 due to start in July. Works have started on the internal fit out, with some corridors and plant rooms ready for the first...

  • 10 West: Project update - July 2015

    Progress to date The project is on schedule and continues to benefit from the good weather conditions: Construction of level 4 has been completed; work on level 5 is now underway and good progress is being made. Internal partitions have...

  • ‘D’ car park near 2 South to close for 3 weeks from 6 Jul

    A gas main is to be installed for the new 10 West building. The route of the main means that 2 South Car Park (D) will have to close for approximately three weeks from Monday 6 July. We apologise for any...

  • Temporary closure of footpath from West car park to Medical Centre

    As part of the 10W project, new gas and data services need to be run from car park D (South of 2 South building) to the new 10W building. The route involves excavating and laying new services along the footpath...

  • 1 West Phase 3: Project Update June 2015

    Midas Construction Limited continue apace with the reconstruction and fit out. Installation of the ductwork for ventilation and infrastructure for the electrical services is currently underway. Works to replace the existing roof with a high performance insulated felt roof have...

  • 10 West: Project Update - June 2015

    Progress to date The project is on program and continues to benefit from the good weather conditions: The construction of level 3 has been completed, level 4 is also making good progress. The erection of the steel frame to the...