Impact of campus investment building projects

Keeping you updated on our current campus building projects

Tagged: 10W

10W construction time lapse videos

  ,

📥  10 West

The construction of 10W has been completed, providing a fantastic modern space to house the Psychology labs, IPR offices and the brand new postgraduate learning zone.

Below are two time-lapse videos showing the construction from start to finish.

 

Building for our future

  , , , ,

📥  10 West, 4 East South

Message from Diane Aderyn, Director of Finance & Commercial Services, as staff move into 10 West:

Dear colleagues

I wanted to give you an update on developments on and off campus in case you were unable to attend Let’s Talk.

Improving our infrastructure is central to our new strategy. We are creating modern, purpose built spaces from which we can increase the volume of our research, grow graduate student numbers, enhance the experience we offer undergraduate students and strengthen our global profile.

Claverton Campus

We have taken possession of 10 West and will start using the building this week.

This will provide state of the art facilities for the Department of Psychology and Institute for Policy Research (IPR) as well as offering study space for postgraduate students on its upper floors.

To the East, we will be moving into 4 East South in July. The main structure will house the Department of Architecture & Civil Engineering with a separate space providing the base for the University’s main computing data centre.

Between them, both buildings increase the space we have available on campus for research, learning and teaching by nearly 10 per cent.

To the South, the project to construct the Milner Centre building is progressing well. Planning consent was secured last month and we are close to appointing contractors, with work on site to start in August.

After Computer Services move into 4 East South, 2 South will be used to accommodate staff as other buildings are refurbished. The area will then be redeveloped to create a range of new science laboratories.

There are also plans for the North of campus that are being worked on as we speak.

City of Bath

In the City, we have received planning consent to transform 18 Manvers Street into a learning zone with office space for student-facing services. We are about to appoint contractors for the extensive redesign to create approximately 1,000m2 of study space and facilities. Together with the 10 West postgraduate facility, this adds 20 per cent more learning space to that offered by the University Library.

We have also put in place measures to accommodate more of our students. We have secured 354 spaces through agreements with five locations in the City and created three new posts to work with private sector landlords and further improve our accommodation enquiries and reception services.

London

You may also have seen the news that we have established a new presence in central London.

83 Pall Mall will provide a base for seminars and programmes from our School of Management, Institute for Policy Research and other departments. Its location will enable us to develop even closer links with national and international policymakers, partners and collaborators.

The recording of my talk is on the Let’s Talk webpages if you would like to see my presentation.

The building work you see happening around you is the physical evidence of the work that is going into developing our new strategy.

As the facilities come on stream, they will provide us with the platform to establish the University as an international leader in graduate education.

 

10 West: Project Update

  , ,

📥  10 West

The project is making good progress and remains on schedule despite recent stormy weather conditions.

  • The North Atrium curtain wall (a weather proof outer layer of the building) has been glazed and works are progressing internally. The scaffolding will be removed from the atrium by the end of the month.
  • Services have been connected, allowing commissioning of water and electricity to start.
  • The installation of vinyl and whiterock in all toilet/shower facilities is nearing completion. Sanitary equipment is also being fitted.
  • Final decorations have begun on all levels and carpet laying has commenced on Level 3.
  • Hard landscaping is progressing well around the building.
  • New smaller site accommodation is in place and the main site offices will be removed in March.

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

 

10 West: Project Update

  , ,

📥  10 West

10 w feb

The project remains on schedule despite the winter weather conditions:

  • Work on the building’s façade is progressing well and the installation of the final composite tiles is nearly finished.
  • Internal works continue to make good progress with the installation of glazed decorative screens.
  • Floor finishings to wet areas are nearly finished.
  • Final fix carpentry is nearly finished.
  • Final finishings to the main entrance and Atrium staircase have begun.
  • Installation of glass balustrades in the Atrium has been completed.
  • Access scaffolding in the atrium is being removed to allow the final works on the floor to begin.
  • Structural work on the main entrance and podium walkway has been completed.
  • Installation of the steel framed walkway to the Podium will begin in early February.
  • Landscaping work has begun and the connection to the 8 West ramp is nearly finished.
  • The site team’s office will be removed in March so that major landscaping works can begin, and a smaller temporary office will be installed.

 

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

Did you know…

Since the start of the construction project the site team has used over 207,200 tea bags, 22.5kg of coffee and 171kg of sugar.

 

10 West: Project Update

  , ,

📥  10 West

The project has made good progress and remains on schedule, despite the halt in construction over the Christmas period:

  • Work on the façade continues on all elevations despite delays due to the recent high winds and heavy rainfall.
  • Screeding (levelled concrete flooring) has now been completed on all levels.
  • Installation of pre-cast concrete planks and precast stairs has been finished in the North elevation.
  • Structural topping (a layer of concrete and wire mesh on top of floor slabs) is now complete throughout the building.
  • Raised access floors on Level 5 are in the final stage.
  • Fitting of balustrade glass within the Atrium has made good progress.
  • Fitting of internal glass partition screens has progressed to Level 4.
  • Mechanical, electrical and second fix carpentry has made excellent progress on all levels
  • Work on the lift infrastructure is now 80% complete.
  • Internal plastering is nearing completion with work remaining on Levels 0 and 1.
  • Installation of White Rock (hygienic wall cladding) has begun in toilets and kitchens.

 

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

 

 

10 West: Project Update

  ,

📥  10 West

The project has made good progress and remains on schedule, despite recent weather conditions.

  • Work continues on the Podium to prepare for the installation of concrete planks on 7 December.
  • Internal work has now commenced on Level 5, coinciding with the installation of lifts.
  • Final work has begun on the building’s façades, including external rendering, fitting glass panes and cosmetic finishes.

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

Installation of cosmetic finishes on the building’s southern façade

Installation of cosmetic finishes on the building’s southern façade

10 West: Project update

  , ,

📥  10 West

Progress to date

The project remains on schedule and the team are well prepared for difficult winter weather conditions.

  • Excellent progress has been made on the façades on all elevations to prepare for installation of final finishings.
  • Work on the roof has nearly finished.
  • Preparation for the installation of photovoltaic panels has begun.
  • Internal works throughout the building are progressing well, and the final joinery stage has begun.
  • Installation of glazed screens will begin soon.
  • Final works within the Atrium and on the feature stairwell have started and should be complete by late December 2015

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

Did you know…?

On 22 October 2015 the Vice-Chancellor, Professor Dame Glynis Breakwell, together with representatives from the University’s Council and Vinci Construction attended a Topping Out ceremony. Topping Out ceremonies are held when a new building reaches its highest point. Traditionally the ceremony is conducted to thank workers for their efforts and to honour their safety.

10W-topout-3

 

10 West reaches ‘high point’ in its development

  , ,

📥  10 West

A special ceremony, dating back thousands of years, took place last week to celebrate a crucial stage in the 10 West building project.

10W-topout-3

 

The 'topping out' of the new multi-million pound building was performed by Vice-Chancellor Professor Dame Glynis Breakwell.

The 'topping out' celebration is held when the highest point of a new building has been constructed. Traditionally it was a celebration to thank workers for their efforts, to honour their safe working, and to wish safety for those about to complete the construction.

Dame Glynis was joined by members of the University Council, representatives from the main contractor Vinci Construction, and other University colleagues including Director of Estates Martyn Whalley.

The new 10 West building is due to open in early 2016 at a cost of around £29m. It will provide state-of-the art new research and teaching space for the expansion of the Department of Psychology as well as a new home for the University's Institute for Policy Research.

Martyn Whalley said: "We are delighted with the progress of this major building project which will provide much needed additional academic space on campus.”

Peter Cole of Vinci Construction, added: "We are extremely pleased to have been awarded this prestigious project, and to be working with an exceptional team of individuals to achieve the best for the University.

“The building works are progressing well and are on programme for a successful completion next April.”

 

 

 

10 West: Project update

  , ,

📥  10 West

Progress to date

The project remains on schedule and made good progress in September:

  • The façade and roof are now mostly water tight which has allowed internal works to restart on Level 5.
  • Access facilities within the Atrium have been completed, ready for future internal work.
  • External work to the podium is underway in preparation for the delivery of stairs and precast planks.
  • Substantial mechanical plant equipment has been delivered and will be installed in the Level 4 plant rooms.
10 West façade from the North

10 West façade from the North

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

Did you know…?

Approximately 450 tons of plasterboard have been used in the building; if the boards were laid end to end they would stretch for 26 miles (double the distance of the Bath to Bristol cycle track).

 

10 West: Project update

  , ,

📥  10 West

Progress to date

We are pleased to report the project is still on schedule

  • The concrete frame is now completed together with the atrium stairs which has allowed the crane to be removed from site.
  • As can be seen from the site, the majority of the windows are in and the larger glazing panels should be completed over the next couple of months.  A number of openings have been left to assist in material deliveries.
Most windows have been fitted

Most windows have been fitted

  • The roofing works are now well advanced and due for completion during October.  A separate temporary crane will be used to get the final materials to the roof. The aim is for the roof to be water tight in late October.
  • Internal partitioning works and M&E installations are progressing up to Level 4.
  • Raised access floors and plastering is well underway on all floors.

We are continuing to hold meetings with the end users of the building; members of the Department of Psychology have visited the site and they were very impressed with the progress.

10 West on schedule for completion

10 West on schedule for completion

Health & Safety

There have been no accidents and regular reviews continue to ensure a safe environment for those working on site and  pedestrians passing by.

Noise

Noise will continue at the same level as in previous months.

Did you know…?

We have over 5 miles of various types of pipework within the building, with 40 engineers working on it.