    Message from Diane Aderyn, Director of Finance & Commercial Services, as staff move into 10 West: Dear colleagues I wanted to give you an update on developments on and off campus in case you were unable to attend Let’s Talk....

  • 4 East South: Project Update

    The project has made good progress despite recent stormy weather conditions. Large segments of the West core are nearing completion which means work can now move on to the East core. Concrete works in the West core are complete. The installation of...

  • 4 East South: Project Update

    January has seen the project move forward considerably: Large areas of the building are now boarded and plastered. Raised access flooring has been laid up to level 5 in the West section. The East exhibition space has been fully boarded, plastered...

  • 4 East South: Project Update

    The project has made good progress during December despite a halt in construction over the Christmas period and the recent bad weather conditions: Screeding (levelled concrete flooring) has been completed on level 4. The underfloor heating system has been installed....

  • 4 East South: Project update

    Progress to date The site team have made excellent progress during October and remain on schedule. The roof has been completed and a weatherproofing will begin in November. Once the roof has been made weather tight internal works will commence....

  • 4 East South: Project update

    Progress to date September was been a busy month: The second double height level has been completed. The reinforced concrete frame has been completed up to Level 6. The erection of cladding between levels 2 and 4 has begun. Construction...

  • 4 East South: Project update

    Progress to date August has been a productive month: The reinforced concrete frame is complete up to Level 5 on the west wing and Level 4 on the east. The first double height studio floor is now completed, the next one...

  • 4 East South: Project update - August 2015

    Progress to date The project is going well, and this month we have made good progress. The reinforced concrete frame up to Level 4 on the West wing, and level 3 on the East has been completed. The West wing...

  • 4 East South: Project update - July 2015

    Progress to date Main build The concrete structure for level 1-2 has been completed with level 3 due to start in July. Works have started on the internal fit out, with some corridors and plant rooms ready for the first...

  • 4 East South: Project Newsletter - May 2015

    Progress to date Main build Work has progressed well over the past month and the team has taken advantage of the good weather. Vertical elements such as columns and core walls have been completed on the West end of the...