  • 4 East South: Project update - July 2015

    Progress to date Main build The concrete structure for level 1-2 has been completed with level 3 due to start in July. Works have started on the internal fit out, with some corridors and plant rooms ready for the first...

  • 4 East South: Project Newsletter - May 2015

    Progress to date Main build Work has progressed well over the past month and the team has taken advantage of the good weather. Vertical elements such as columns and core walls have been completed on the West end of the...

  • 4 East South: Project Newsletter - April 2015

    Progress to date Main build Despite minor set backs due to high winds and bad weather the project is on schedule. The final installment of ground floor slabs is complete. Installation of the building frame and columns has started and...