Impact of campus investment building projects

Keeping you updated on our current campus building projects

Tagged: manvers street

Manvers Street project update

  , ,

📥  Manvers Street

Level 1

  • Internal finishes have started on level 1 following the completion of the external tanking and waterproofing.
  • Dribuild and the supply chain are working hard to complete this area as soon as possible following delays encountered due to council restrictions.

Level 2

  • Works on Level 2 are progressing well with suspended ceilings and decorations ongoing

External Works

  • Window replacement works are almost complete - including plastering and decorations.
  • The lift shaft construction is complete and the new passenger lift is being installed.
  • The front courtyard waterproofing and tanking work is almost complete.

Access routes across the site are maintained for the UOB staff working on Level 4.

The access routes will be changed after Christmas when staff will be need to use the main entrance to enable work to the existing staff entrance and stairwell to be carried out.

 

Manvers Street Project Update

  ,

📥  Manvers Street

External works

  • Window replacements are progressing well on Levels 2 and 3.
  • Concrete panels and glazing to the front elevation have been removed and will be replaced with curtain wall glazing.
  • Bath Stone cladding is progressing to the new lift shaft on the South elevation and is due to be completed this week.
  • The front courtyard waterproofing and tanking works are progressing.
  • Roofing works are complete and the new air handling unit will be lifting onto the roof with a mobile crane.

Access routes across the site are maintained for the University staff working on Level 4.  The access routes will be amended as the works progress.
Internal works

Level 1

  • Internal tanking and waterproofing works are complete.
  • Mechanical, Electrical and Carpentry works are progressing well.
  • Plasterboarding is ongoing and plastering will follow.

Level 2

  • Mechanical, Electrical and Carpentry works are progressing well.
  • Decorations and finishes works have commenced.

Level 3

  • The toilet refurbishments are complete and handed over for use by occupants.
  • The staff have now been relocated from the South end of Level 4 onto Level 3 in preparation for the lift shaft breakthroughs.

All works on Level 3 will be completed by the end of November.

 

18 Manvers Street project update

  ,

📥  Manvers Street

The refurbishment works continue to progress well.

  • Level 1 floor screed has been laid and partition works are ongoing.
  • Level 1 inner courtyard walls have been built and initial fitting of Mechanical and Electrical (M&E) installations are progressing well.
  • Lift shaft cladding is progressing and stonework starts next week.
  • Level 2 initial fixing of cables and pipework are complete.
  • Plastering works to walls on level 2 are almost complete and carpentry works, including fitting of doors and frames, are progressing well.
  • New ceilings and final fixing of cables, power outlets, lighting and heating systems will start next week on level 2.
  • Levels 3 and 4 alteration works are progressing well.
  • The recent power and water shutdowns took place successfully to help minimise disruption to University staff on Level 4.
  • Level 3 is being prepared for temporary staff moves for the payroll team from end of October.
  • Works to the forecourt will progress, including insulation and waterproofing works.
  • Re-cabling of the data services for Level 2 will start soon.
  • Installation of the new air handling unit is planned.

Noise and dust levels are continually monitored. Please feel free to contact Dribuild Site Manager, Tom Young, on 07843 980398 with any queries.