project update

  • The Milner Centre for Evolution Project update

    Welcome to the third monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution project. Our site manager, Firhan Rudorf-Saeed is on site throughout the working day, and should be the first point of...

  • Polden project update

    Welcome to the third monthly update aimed at keeping you up to speed on the new Polden Student Accommodation project. Our Project Manager Steve Phillips is on site throughout the working day, and should be the first point of contact...

  • Manvers Street project update

    Level 1 Internal finishes have started on level 1 following the completion of the external tanking and waterproofing. Dribuild and the supply chain are working hard to complete this area as soon as possible following delays encountered due to council...

  • Manvers Street Project Update

    External works Window replacements are progressing well on Levels 2 and 3. Concrete panels and glazing to the front elevation have been removed and will be replaced with curtain wall glazing. Bath Stone cladding is progressing to the new lift...

  • 18 Manvers Street project update

    The refurbishment works continue to progress well. Level 1 floor screed has been laid and partition works are ongoing. Level 1 inner courtyard walls have been built and initial fitting of Mechanical and Electrical (M&E) installations are progressing well. Lift...

  • 18 Manvers Street project update

    We are pleased to report that refurbishment works are progressing well: Refurbishment works continue to progress well on Levels 1 and 2. The structural steel frame for the new lift shaft to the Southern end of the building has been...

  • 18 Manvers Street project update

    We are pleased to report that refurbishment works are progressing well: The front forecourt hoarding has been constructed. Level 1 drainage works are progressing well, and most of the concrete floor slab breaking out process has now been completed. Piling...

  • 18 Manvers Street project update

    Work has now started on transforming the former police station into a new student learning zone and provide a city centre location for student-facing services. The contractor Dribuild has erected hoardings around the building and work on the front forecourt...

  • 10 West: Project Update

    The project is making good progress and remains on schedule despite recent stormy weather conditions. The North Atrium curtain wall (a weather proof outer layer of the building) has been glazed and works are progressing internally. The scaffolding will be...

  • 4 East South: Project Update

    The project has made good progress despite recent stormy weather conditions. Large segments of the West core are nearing completion which means work can now move on to the East core. Concrete works in the West core are complete. The installation of...