10 West: Project Update - June 2015

Posted in: 10 West

Progress to date

The project is on program and continues to benefit from the good weather conditions:

  • The construction of level 3 has been completed, level 4 is also making good progress.
  • The erection of the steel frame to the west block and atrium is now completed.
  • The facades are now commencing which will allow the internal trades to start work in the near future.
  • The insitu reinforced concrete feature atrium staircase is now in progress.

Ongoing reviews continue with the final users of the building, the Department of Psychology and the Office of Policy and Planning, refining detailed requirements and furniture procurement.

Health & Safety

Extra measures and precautions remain in place around the site when construction vehicles leave and are being monitored to ensure safety. These include measures such as banksmen who are helping vehicles to safely leave the site.

To date there have been no injuries or accidents, the team continue to achieve exemplary levels of safety.

Noise

The noise levels will continue to the same level as they have been in the previous month.

Did you know?...

This project is one of the projects being showcased by the Institute of Civil Engineers as a major project contributing to the local infrastructure, economy and employment.

General queries can be addressed to Estates Helpdesk

Please also see Campus investments webpages and Estates webpages

IMG_1086
10 West progress to date

Posted in: 10 West

Respond

  • (we won't publish this)

Write a response