Gill Smith
Internal Communications Officer
-
Gill SmithMarch 1, 2017
Polden: Section of Quarry Rd to close from Mon 6 Mar
To facilitate the construction of the Polden accommodation building, changes are required to the roads on the west of the Claverton campus for the duration of the project. Completion is scheduled for summer 2018; we apologise for any inconvenience. Latest update:...
-
Gill SmithJuly 4, 2016
ACE & Computing Services staff move into 4 East South
Staff have started moving into our latest addition to campus - 4 East South. The £23m building will create research and teaching space for the Faculty of Engineering & Design as well as housing a cutting-edge computing data centre. Teams...
-
Gill SmithJune 22, 2016
Refurbishment works in 2 East, 4 East & 6 East
Major refurbishment works, known as the ‘ACER (Backfill) Project’, will be taking place in the 2 East, 4 East & 6 East buildings over the summer. The project will create: refurbished and enlarged research space in the Department of Architecture...
More from this author
-
Gill SmithMay 4, 2016
Building for our future
Message from Diane Aderyn, Director of Finance & Commercial Services, as staff move into 10 West: Dear colleagues I wanted to give you an update on developments on and off campus in case you were unable to attend Let’s Talk....
-
Gill SmithAugust 27, 2015
4 East South: Project update
Progress to date August has been a productive month: The reinforced concrete frame is complete up to Level 5 on the west wing and Level 4 on the east. The first double height studio floor is now completed, the next one...
-
Gill SmithAugust 27, 2015
10 West: Project update
Progress to date We are pleased to report the project is still on schedule The concrete frame is now completed together with the atrium stairs which has allowed the crane to be removed from site. As can be seen from...
-
Gill SmithJuly 7, 2015
4 East South: Project update - July 2015
Progress to date Main build The concrete structure for level 1-2 has been completed with level 3 due to start in July. Works have started on the internal fit out, with some corridors and plant rooms ready for the first...
-
Gill SmithJuly 7, 2015
10 West: Project update - July 2015
Progress to date The project is on schedule and continues to benefit from the good weather conditions: Construction of level 4 has been completed; work on level 5 is now underway and good progress is being made. Internal partitions have...
-
Gill SmithJuly 2, 2015
‘D’ car park near 2 South to close for 3 weeks from 6 Jul
A gas main is to be installed for the new 10 West building. The route of the main means that 2 South Car Park (D) will have to close for approximately three weeks from Monday 6 July. We apologise for any...
-
Gill SmithJune 18, 2015
Temporary closure of footpath from West car park to Medical Centre
As part of the 10W project, new gas and data services need to be run from car park D (South of 2 South building) to the new 10W building. The route involves excavating and laying new services along the footpath...