Sophie Madison

  • 4 East South: Project update

    Despite the recent windy conditions and heavy rainfall progress has been good. The building’s West core has received a weather proof coating. All windows have been installed on the West core. The West core is scheduled to be completely water tight...

  • 10 West: Project Update

    The project has made good progress and remains on schedule, despite recent weather conditions. Work continues on the Podium to prepare for the installation of concrete planks on 7 December. Internal work has now commenced on Level 5, coinciding with...

  • 10 West: Project update

    Progress to date The project remains on schedule and the team are well prepared for difficult winter weather conditions. Excellent progress has been made on the façades on all elevations to prepare for installation of final finishings. Work on the...

  • 4 East South: Project update

    Progress to date The site team have made excellent progress during October and remain on schedule. The roof has been completed and a weatherproofing will begin in November. Once the roof has been made weather tight internal works will commence....

  • 10 West reaches ‘high point’ in its development

    A special ceremony, dating back thousands of years, took place last week to celebrate a crucial stage in the 10 West building project.   The 'topping out' of the new multi-million pound building was performed by Vice-Chancellor Professor Dame Glynis Breakwell. The 'topping out'...

  • 10 West: Project update

    Progress to date The project remains on schedule and made good progress in September: The façade and roof are now mostly water tight which has allowed internal works to restart on Level 5. Access facilities within the Atrium have been completed,...

  • 4 East South: Project update

    Progress to date September was been a busy month: The second double height level has been completed. The reinforced concrete frame has been completed up to Level 6. The erection of cladding between levels 2 and 4 has begun. Construction...

  • 4 East South: Project update - August 2015

    Progress to date The project is going well, and this month we have made good progress. The reinforced concrete frame up to Level 4 on the West wing, and level 3 on the East has been completed. The West wing...

  • 10 West: Project update - August 2015

    Progress to Date Despite recent wet weather conditions, the project is still on schedule. Construction of level 5 has been completed; work on level 6 is now underway and good progress is being made Both north and south concrete stairs...