10 West: Project Update

Posted in: 10 West

The project has made good progress and remains on schedule, despite the halt in construction over the Christmas period:

  • Work on the façade continues on all elevations despite delays due to the recent high winds and heavy rainfall.
  • Screeding (levelled concrete flooring) has now been completed on all levels.
  • Installation of pre-cast concrete planks and precast stairs has been finished in the North elevation.
  • Structural topping (a layer of concrete and wire mesh on top of floor slabs) is now complete throughout the building.
  • Raised access floors on Level 5 are in the final stage.
  • Fitting of balustrade glass within the Atrium has made good progress.
  • Fitting of internal glass partition screens has progressed to Level 4.
  • Mechanical, electrical and second fix carpentry has made excellent progress on all levels
  • Work on the lift infrastructure is now 80% complete.
  • Internal plastering is nearing completion with work remaining on Levels 0 and 1.
  • Installation of White Rock (hygienic wall cladding) has begun in toilets and kitchens.

 

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

 

Posted in: 10 West