10 West

  • Polden project update

    Welcome to the third monthly update aimed at keeping you up to speed on the new Polden Student Accommodation project. Our Project Manager Steve Phillips is on site throughout the working day, and should be the first point of contact...

  • 10W construction time lapse videos

    The construction of 10W has been completed, providing a fantastic modern space to house the Psychology labs, IPR offices and the brand new postgraduate learning zone. Below are two time-lapse videos showing the construction from start to finish.

  • Building for our future

    Message from Diane Aderyn, Director of Finance & Commercial Services, as staff move into 10 West: Dear colleagues I wanted to give you an update on developments on and off campus in case you were unable to attend Let’s Talk....

  • 10 West: Project Update

    The project is making good progress and remains on schedule despite recent stormy weather conditions. The North Atrium curtain wall (a weather proof outer layer of the building) has been glazed and works are progressing internally. The scaffolding will be...

  • 10 West: Project Update

    The project remains on schedule despite the winter weather conditions: Work on the building’s façade is progressing well and the installation of the final composite tiles is nearly finished. Internal works continue to make good progress with the installation of...

  • 10 West: Project Update

    The project has made good progress and remains on schedule, despite the halt in construction over the Christmas period: Work on the façade continues on all elevations despite delays due to the recent high winds and heavy rainfall. Screeding (levelled concrete flooring) has...

  • 10 West: Project update

    Progress to date The project remains on schedule and made good progress in September: The façade and roof are now mostly water tight which has allowed internal works to restart on Level 5. Access facilities within the Atrium have been completed,...

  • 10 West: Project update

    Progress to date We are pleased to report the project is still on schedule The concrete frame is now completed together with the atrium stairs which has allowed the crane to be removed from site. As can be seen from...

  • 10 West: Project update - August 2015

    Progress to Date Despite recent wet weather conditions, the project is still on schedule. Construction of level 5 has been completed; work on level 6 is now underway and good progress is being made Both north and south concrete stairs...

  • 10 West: Project update - July 2015

    Progress to date The project is on schedule and continues to benefit from the good weather conditions: Construction of level 4 has been completed; work on level 5 is now underway and good progress is being made. Internal partitions have...