Welcome to the monthly update focused on keeping you up to speed on progress being made at the University of Bath, School of Management project. Good progress has been made on all fronts internally and externally for the project with...
Internally the team have been pushing on all floors. At basement level the team continue with the installation of the M&E services. Works to complete the drylining at the cores of these levels are underway. The main auditorium continues to...
Externally the public realm works are changing the neighbouring landscape but giving an insight into the open space that will be to the north elevation. Externally to the building the façade works are progressing well with good progress made in...