  • 10 West: Project update - August 2015

    Progress to Date Despite recent wet weather conditions, the project is still on schedule. Construction of level 5 has been completed; work on level 6 is now underway and good progress is being made Both north and south concrete stairs...

  • 10 West: Project update - July 2015

    Progress to date The project is on schedule and continues to benefit from the good weather conditions: Construction of level 4 has been completed; work on level 5 is now underway and good progress is being made. Internal partitions have...

  • ‘D’ car park near 2 South to close for 3 weeks from 6 Jul

    A gas main is to be installed for the new 10 West building. The route of the main means that 2 South Car Park (D) will have to close for approximately three weeks from Monday 6 July. We apologise for any...

  • 10 West: Project Newsletter - May 2015

    Progress to date The project is on program and is benefiting from the good weather conditions: Works on the underdeck and water main connections have been completed ahead of schedule. The construction of level 1 has been completed, level 2...

  • 10 West: Project Newsletter - April 2015

    Progress to date The project is making excellent progress despite the high wind and bad weather experienced in March. Extra measures and precautions have been introduced when construction vehicles leave the site, such as banksmen that are helping vehicles to...