June 2015

  • Temporary closure of footpath from West car park to Medical Centre

    As part of the 10W project, new gas and data services need to be run from car park D (South of 2 South building) to the new 10W building. The route involves excavating and laying new services along the footpath...

  • 1 West Phase 3: Project Update June 2015

    Midas Construction Limited continue apace with the reconstruction and fit out. Installation of the ductwork for ventilation and infrastructure for the electrical services is currently underway. Works to replace the existing roof with a high performance insulated felt roof have...

  • 10 West: Project Update - June 2015

    Progress to date The project is on program and continues to benefit from the good weather conditions: The construction of level 3 has been completed, level 4 is also making good progress. The erection of the steel frame to the...

  • 4 East South: Project Update - June 2015

    Main build The first sets of precast concrete planks have started on the west core of the building. The preparation of the east side has been completed and the planks will be arriving in the next couple of weeks. Two...