June 2018
-
Polden development update - June 2018
The outside of our building is taking shape now, with progress to the stone cladding and other elements of the façade. We’ve also removed our tower crane from the site, which is allowing us to progress with landscaping works to...
-
The Milner Centre for Evolution Project Update - June 2018