1 West Phase 3: Project Update June 2015
Midas Construction Limited continue apace with the reconstruction and fit out. Installation of the ductwork for ventilation and infrastructure for the electrical services is currently underway. Works to replace the existing roof with a high performance insulated felt roof have...
-
10 West: Project Update - June 2015
Progress to date The project is on program and continues to benefit from the good weather conditions: The construction of level 3 has been completed, level 4 is also making good progress. The erection of the steel frame to the...
-
4 East South: Project Update - June 2015
Main build The first sets of precast concrete planks have started on the west core of the building. The preparation of the east side has been completed and the planks will be arriving in the next couple of weeks. Two...