January 2016

  • 4 East South: Project Update

    The project has made good progress during December despite a halt in construction over the Christmas period and the recent bad weather conditions: Screeding (levelled concrete flooring) has been completed on level 4. The underfloor heating system has been installed....

  • 10 West: Project Update

    The project has made good progress and remains on schedule, despite the halt in construction over the Christmas period: Work on the façade continues on all elevations despite delays due to the recent high winds and heavy rainfall. Screeding (levelled concrete flooring) has...