July 2018
-
New gym project update July 2018
Good progress has been made internally and externally on the project. Externally the drainage works are nearing completion and if you have an eagle eye you may see the balustrade currently in situ before it is dismantled to receive its...
-
The Milner Centre for Evolution Project Update - July 2018
Our site managers Tomasz Magiera, Firhan Rudorf-Saeed and Chris Johnson are on site throughout the working day. We are continuing to hold fortnightly meetings with the users of Building 4SA, and attend the monthly University Contractor’s meeting with a view...
-
Polden development update - July 2018
The stone cladding is progressing rapidly, with most progress being made to the rear of the building to allow our landscaping works to progress. We are busy laying our kerbstones and edgings, ahead of the block paving works to the...