  • 10 West: Project Newsletter - May 2015

    Progress to date The project is on program and is benefiting from the good weather conditions: Works on the underdeck and water main connections have been completed ahead of schedule. The construction of level 1 has been completed, level 2...

  • 4 East South: Project Newsletter - May 2015

    Progress to date Main build Work has progressed well over the past month and the team has taken advantage of the good weather. Vertical elements such as columns and core walls have been completed on the West end of the...

  • 4 East South: Project Newsletter - April 2015

    Progress to date Main build Despite minor set backs due to high winds and bad weather the project is on schedule. The final installment of ground floor slabs is complete. Installation of the building frame and columns has started and...

  • 10 West: Project Newsletter - April 2015

    Progress to date The project is making excellent progress despite the high wind and bad weather experienced in March. Extra measures and precautions have been introduced when construction vehicles leave the site, such as banksmen that are helping vehicles to...