Polden Development Update - May
Welcome to the 16th monthly update on the new Polden Corner Student Accommodation project. You may have noticed the progress being made on the stone cladding on the exterior of the building. This progress will allow us to remove some...
-
jjw72April 10, 2018
Polden development update - April
Welcome to the 15th monthly update with news to keep you informed on the new Polden Corner Student Accommodation project. The outside of the building is changing rapidly, all structural work is now completed and the final tower crane is...
-
The Milner Centre for Evolution project update
Welcome to the 15th monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution Project. Work to install the roof is continuing and the Bauder system has been installed to 90% of the main...
More from this author
-
jjw72March 28, 2018
Sports Training Village Gym Extension – March 2018
Welcome to the second update on the construction of the STV Gym Extension. Over the last six weeks good progress has been made despite some unseasonal weather conditions. The building frame has been constructed, and the concrete plank floors are...
-
jjw72March 5, 2018
Polden development update
Welcome to the 14th monthly update with news to keep you informed on the new Polden Student Accommodation project. February has seen many changes on the project, as work on both the outside and the inside of the building progresses....
-
jjw72February 14, 2018
The Milner Centre for Evolution project update
Welcome to the 13th monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution Project. Work to install the roof and make the building water tight is still taking place with 80% of the...
-
jjw72February 14, 2018
Sport Training Village: Gym Extension, February 2018
This is the first in a series of monthly updates which will track the construction of the new gym extension and provide an insight into the work going-on behind the scenes to create a high quality sports facility. The Gym...
-
jjw72February 7, 2018
Polden development update
Welcome to the 13th monthly update with news to keep you informed on the new Polden Student Accommodation project. January has been another busy month with progress being made on the inside of the building as work continues on the...
-
jjw72December 7, 2017
Repairs to Virgil Building courtyard