Impact of campus investment building projects
Keeping you updated on our current campus building projects
Keep up to date with new posts
Subscribe-
New gym project update July 2018
Good progress has been made internally and externally on the project. Externally the drainage works are nearing completion and if you have an eagle eye you may see the balustrade currently in situ before it is dismantled to receive its...
-
The Milner Centre for Evolution Project Update - July 2018
Our site managers Tomasz Magiera, Firhan Rudorf-Saeed and Chris Johnson are on site throughout the working day. We are continuing to hold fortnightly meetings with the users of Building 4SA, and attend the monthly University Contractor’s meeting with a view...
-
Polden development update - July 2018
The stone cladding is progressing rapidly, with most progress being made to the rear of the building to allow our landscaping works to progress. We are busy laying our kerbstones and edgings, ahead of the block paving works to the...
Latest posts
-
Polden development update - June 2018
The outside of our building is taking shape now, with progress to the stone cladding and other elements of the façade. We’ve also removed our tower crane from the site, which is allowing us to progress with landscaping works to...
-
The Milner Centre for Evolution Project Update - June 2018
Roof works are continuing and the Bauder roof system has been installed to 98% of the main roof. The lower balcony is approx. 98% complete with just finishing works remaining. The small roof over the entrance door is approx. 80%...
-
Polden Development Update - May
Welcome to the 16th monthly update on the new Polden Corner Student Accommodation project. You may have noticed the progress being made on the stone cladding on the exterior of the building. This progress will allow us to remove some...
-
Polden development update - April
Welcome to the 15th monthly update with news to keep you informed on the new Polden Corner Student Accommodation project. The outside of the building is changing rapidly, all structural work is now completed and the final tower crane is...
-
The Milner Centre for Evolution project update
Welcome to the 15th monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution Project. Work to install the roof is continuing and the Bauder system has been installed to 90% of the main...
-
Sports Training Village Gym Extension – March 2018
Welcome to the second update on the construction of the STV Gym Extension. Over the last six weeks good progress has been made despite some unseasonal weather conditions. The building frame has been constructed, and the concrete plank floors are...
-
Polden development update
Welcome to the 14th monthly update with news to keep you informed on the new Polden Student Accommodation project. February has seen many changes on the project, as work on both the outside and the inside of the building progresses....