Impact of campus investment building projects

Keeping you updated on our current campus building projects

The Milner Centre for Evolution project update

📥  Milner Centre

Welcome to the 13th monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution Project.

Work to install the roof and make the building water tight is still taking place with 80% of the Bauder roof system installed to the main roof, with a view to work starting on the roof of the lower balcony in the next week.

Internally, the walls are continuing to go up on both floors, and the ductwork and housing for all of the electrical and data cabling is currently being installed. The works associated with the underfloor heating and the screed is now complete. The automatic front door is on site and will be installed in the coming weeks.

Both the brickwork and stonework is continuing to be installed all around the perimeter at low and high level with the East elevation of the building soon to be complete. The installation of the grey Kingspan cladding is nearly complete with only a few areas remaining to be covered up. The cream/white Marley Eternit cladding has started to be installed on the North Elevation. Some of the glazing has also been installed to the curtain walling section at low level and also on the North Elevation.

 

 

The transformer for the building has been positioned on site, with a view to installing its GRP housing unit in the next week. Drainage work is currently ongoing. We have installed the attenuation tank and are in the process of backfilling and reinstating the car park. The contractor is working closely with the University’s Estates & Security teams to minimise any disruption and work is continuing to take place over the weekends.

 

Sport Training Village: Gym Extension, February 2018

  

📥  STV gym extension

This is the first in a series of monthly updates which will track the construction of the new gym extension and provide an insight into the work going-on behind the scenes to create a high quality sports facility.

The Gym Extension will provide an additional 940m² of floor space to the Sports Training Village split across two floors, with enough room to accommodate more than 200 users.

The contractor Melhuish & Saunders Ltd (M&S) started construction in November. The initial focus was on the underground infrastructure and creating sufficient working room at the side of the Sports Hall to build a new ramp and stepped access.

Creating a new access point into the Sports Hall early in the programme will free-up the construction site for M&S and enable them to start setting out the foundations and preparing the site for the building’s steel frame.

It is anticipated that the steel deliveries will start from 19 February 2018. These will generate some increased traffic which will be coordinated with the neighbouring University facilities of BioMechanics, STV and the Edge Theatre.

 

Polden development update

📥  Polden

Welcome to the 13th monthly update with news to keep you informed on the new Polden Student Accommodation project.

January has been another busy month with progress being made on the inside of the building as work continues on the concrete frame.

For safety reasons, due to very high winds, the dismantling of the first tower crane has been postponed and a new date booked in for mid-February. Everyone is hoping for light winds and good weather on the day! We will notifying everyone closer to the time, to ensure the crane’s transport vehicles pass smoothly through the campus.

The outside of the building is changing every day, with large sections of curtain walling now being installed to the staircores, roofing work is progressing well and hundreds of brackets are being installed to carry the stone cladding system.  You will see the first stone on the building in the middle of February.

Work to connect the water supply from Wessex House to the Polden project is also taking place and we appreciate your patience while this essential work is carried out.

Work on the rear of the building, between the new accommodation and Polden Court, will be starting soon to install important underground services that will bring power and water to the scheme.

Inside the building, doors are being fitted, more floors are being laid and the lifts are even taking shape.  The internal ‘fit-out’ of three out of the four blocks has also started.

The construction team will continue to work closely with the University Estates, AHS, and Security teams to minimise disruption as much as possible.

How Polden will look when it is finished

 

Polden development update

📥  Polden, Polden accommodation, Uncategorized

Welcome to the twelfth monthly update with news to keep you informed on the new Polden Student Accommodation project.

December has been yet another very busy month, despite the inclement weather the concrete frame has continued to progress, whilst inside the building  plastering and decorating are picking up pace!

Due to the bad weather, the first tower crane dismantle has been delayed and will now remain in place until the end of January.  The build team continue to liaise with all relevant University departments on all deliveries expected on the campus to minimise disruption as much as possible.

Outside, the builders are installing more windows and façade boarding and have started installing brackets for the cladding system.  They are also completing drainage works in the ground, so they can clear the way for the architectural finishes to the façades. Inside the building, plastering progress is increasing and carpenters are now on site, preparing to install many thousands of meters of skirting boards and several hundred door frames.  The carpenters are also starting to prepare the floors, ready for furniture to be installed on top.

The forthcoming month will see the pace of construction works continue to increase.  You will see significant changes to the façade of the buildings while internally more and more bedrooms will be formed and progressed.

Your continued patience and understanding whilst construction works are ongoing is very much appreciated, and the construction team will continue to work closely with the University Estates, AHS, and Security teams to minimise disruption as much as possible.

Current site

 

The Milner Centre for Evolution project update

📥  Uncategorized

Welcome to the twelfth monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution Project. Site managers Tomasz Magiera, Firhan Rudorf-Saeed and Andy Gimber are on site throughout the working day and should be the first point of contact for any issues. The team are continuing to hold weekly meetings with the users of Building 4SA, and attend the monthly University Contractor’s meeting with a view to keeping our staff and students informed of our works and to give notice of any potential disruption.

Works to install the roof and make the building substantially water tight are still ongoing. The initial layer of vapour barrier has been installed across the different steps in the roof, and the works are now focussing on installing the insulation and the rest of the Bauder roof system. Internal walls are continuing to go up on both floors with the ductwork and necessary containment for all of the electrical equipment currently being installed. The build team are also just over midway into the works associated with screeding the underfloor heating areas.

Both the brickwork and stonework is continuing to be installed all around the perimeter at low and high level. The installation of the grey Kingspan cladding is nearly complete with only a few areas remaining to be covered up. The next sequence of works will see the white/cream Marley Eternit cladding panels being installed to the North elevation.

The plant compound has now been formed which is the housing unit for the building’s transformers and generators. This phase will also see the remaining drainage works being carried out to conclusion while the investigation works for the attenuation tank is ongoing.

As with last month’s update, the construction team would like to make it know that they are continuously working closely with the University’s Estates & Security teams to make sure that this works has a minimal effect on the users of the car park. In agreement with the University, there will be building work over the next few weekends.

As always, we appreciate your patience and understanding whilst the construction phase is ongoing.

Current site

 

Polden development update

📥  Polden

Welcome to the eleventh monthly update with news to keep you informed on the new Polden Student Accommodation project.

November has been yet another very busy month, with concrete frame to the last block nearing completion and work now well-underway on the internal fit-out.

The first two blocks are now sufficiently progressed to allow one of the two Tower Cranes to be dismantled.  This will be taking place towards the end of December.  The build team continue to liaise with all relevant university departments on all deliveries expected on the campus to minimise disruption as much as possible.

The appearance of the first and second buildings is changing practically on a daily basis; a significant number of windows are now installed and we are about to commence setting out of our cladding system.

Internally the bedrooms are now taking shape, with plasterboard works progressing well and mechanical and electrical installations moving ahead of this.  Carpenters will also be starting work on the internal joinery after Christmas. The forthcoming month will see the pace of construction works increase.  You will see significant changes to the façade of the buildings and internally more and more bedrooms will be formed.

The build team would like to remind staff and students that they appreciate all your patience and understanding whilst the construction work is ongoing, and that they continue to work closely with the University Estates, AHS, and Security teams to minimise disruption as much as possible.

 

Repairs to Virgil Building courtyard

  , , , ,

📥  The Virgil Building

Essential resurfacing work to the courtyard at the Virgil Building will begin on 13 December and take approximately two to three weeks to complete.

To keep any disruption to a minimum, the majority of the heavy work will take place over the weekend of 16 and 17 December.

Drainage and remedial work will take place outside of these dates which may cause some noise disruption. We apologise in advance for any inconvenience caused.

 

The Milner Centre for Evolution project update

  , ,

📥  Milner Centre

Welcome to the eleventh monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution Project.

Site managers Tomasz Magiera, Firhan Rudorf-Saeed and new addition to the team, Andy Gimber, are on site throughout the working day. They should be the first point of contact for any issues and are continuing to hold weekly meetings with the users of Building 4SA. They also attend the monthly University contractor’s meeting with a view to keeping staff and students informed of the works and to give notice of any potential disruption.

Works to install the roof and make the building substantially water tight are currently ongoing, and this will be achieved as soon as the initial layer of vapour barrier is installed. Internally, the walls are continuing to go up on both floors with the duct work and necessary containment for all of the electrical and data currently being installed. The exposed soffits in the offices have now been decorated and finished to a high standard. The team will be starting the screeding works for the underfloor heating in the coming weeks.

Externally, the building is continuing to take shape. The brickwork and stonework is being installed all around the perimeter at low and high level, and more windows have now been installed on all elevations. The installation of the cladding is continuing to progress with the grey Kingspan on the South and West elevations.

The next phase of groundwork has also begun this month which will see the plant compound being excavated in preparation for the housing unit for the building’s transformers and generators. This phase will also see the remaining drainage works being carried out to conclusion. The investigation works for the attenuation tank have started this week, and the build team will be working closely with our Estates and Security teams to make sure that this works has a minimal effect on the users of the car park.

In agreement with the University, builders will be working over the next two weekends. Please note that the site will be shut for the Christmas break from Friday 25 December and will be reopening on Tuesday 2 January 2018.

As always, we appreciate your patience and understanding whilst the construction phase is ongoing.

 

The Milner Centre for Evolution Project update

📥  Uncategorized

Welcome to the tenth monthly update aimed at keeping you up to speed on the new Milner Centre for Evolution Project. Site managers Tomasz Magiera and Firhan Rudorf-Saeed are on site throughout the working day and should be the first point of contact for any issues. They are continuing to hold weekly meetings with the users of Building 4SA, and attend the monthly University Contractor’s meeting with a view to keeping staff and students informed of our works and to give notice of any potential disruption.

Works to install the roof and make the building substantially water tight have begun, and this will be achieved as soon as the initial layer of vapour barrier is installed.

As well as the ground floor, the internal walls have started to go up on the first floor, along with containment baskets for all of the cables and ventilation duct work within the building. The exposed soffits in the offices have started to be decorated and will be finished soon.

Externally, the building is continuing to take shape with brickwork being installed around the perimeter at low level, with a number of windows now installed on the South and East elevations. The installation of the cladding has begun this month and, as well as the grey Kingspan cladding panels, the site has also taken delivery of the Marley Eternit panels and cladding panels that make up the unique DNA strand on the North elevation.

The investigation works for the attenuation tank are still not planned and, as reported in last month’s update, WRW will endeavour to give the University adequate warning as to when the works will be carried out.

Last month was particularly busy with site visits most notably on Monday 9 October when the University played host to Dr Milner, and around 50 VIP guests and University staff with the building’s Topping Out Ceremony. WRW are also pleased to have taken 21 First Year Civil Engineering students on a tour of the building. Lots of smiles and positive feedback has been received from both of these visits.

As always, we appreciate your patience and understanding whilst the construction phase is ongoing.

Current site

 

Polden development update

📥  Uncategorized

Welcome to the tenth monthly update with news to keep you informed on the new Polden Student Accommodation project.

October has been yet another very busy month, with the main frame to the block closest to the West Car Park entrance complete and the fit-out underway.

The concrete frames to the remaining blocks continue to progress at pace with most of the concrete frame works planned to be complete by Christmas.  The construction team continue to liaise with all relevant university departments on all deliveries expected on the campus to minimise disruption as much as possible.

The appearance of the first and second buildings is now changing on a daily basis; with the weather defence board being fixed and widows now being installed also.

Internally many of the bedrooms in the first block have been formed with the bathroom pods now in position. The mechanical and electrical installation is also now underway.

The forthcoming month will be busier still, with construction of the second concrete frame nearing completion and the main external façade works to enclose the structure commencing.  This will further enable the team to progress with the internal fit-out trades.

We appreciate all your patience and understanding whilst the construction work is ongoing, with contractors working closely with the University Estates, AHS, and Security teams to minimise disruption as much as possible.

Current site