Gill Smith

Internal Communications Officer

More from this author

  • Building for our future

    Message from Diane Aderyn, Director of Finance & Commercial Services, as staff move into 10 West: Dear colleagues I wanted to give you an update on developments on and off campus in case you were unable to attend Let’s Talk....

  • 4 East South: Project update

    Progress to date August has been a productive month: The reinforced concrete frame is complete up to Level 5 on the west wing and Level 4 on the east. The first double height studio floor is now completed, the next one...

  • 10 West: Project update

    Progress to date We are pleased to report the project is still on schedule The concrete frame is now completed together with the atrium stairs which has allowed the crane to be removed from site. As can be seen from...

  • 4 East South: Project update - July 2015

    Progress to date Main build The concrete structure for level 1-2 has been completed with level 3 due to start in July. Works have started on the internal fit out, with some corridors and plant rooms ready for the first...

  • 10 West: Project update - July 2015

    Progress to date The project is on schedule and continues to benefit from the good weather conditions: Construction of level 4 has been completed; work on level 5 is now underway and good progress is being made. Internal partitions have...

  • ‘D’ car park near 2 South to close for 3 weeks from 6 Jul

    A gas main is to be installed for the new 10 West building. The route of the main means that 2 South Car Park (D) will have to close for approximately three weeks from Monday 6 July. We apologise for any...

  • Temporary closure of footpath from West car park to Medical Centre

    As part of the 10W project, new gas and data services need to be run from car park D (South of 2 South building) to the new 10W building. The route involves excavating and laying new services along the footpath...