Impact of campus investment building projects
Keeping you updated on our current campus building projects
Keep up to date with new posts
Subscribe-
School of Management Project Update - August 2021
Welcome to the monthly update focused on keeping you up to speed on progress being made at the University of Bath, School of Management project. Good progress has been made on all fronts internally and externally for the project with...
-
School of Management Building Project Update - July 2021
Internally the team have been pushing on all floors. At basement level the team continue with the installation of the M&E services. Works to complete the drylining at the cores of these levels are underway. The main auditorium continues to...
-
School of Management Building Project Update - June 2021
Externally the public realm works are changing the neighbouring landscape but giving an insight into the open space that will be to the north elevation. Externally to the building the façade works are progressing well with good progress made in...
Latest posts
-
School of Management Project Update - May 2021
The project continues to progress in all areas with the internal fit out but also significant changes to the external space with the start of public realm works. Externally the elevations of the building continue to change. Since the blog...
-
School of Management Project Update - April 2021
Externally we continue with façade works to the building whilst commencing with new elements to the north compound. Internally we progress with the fit out whilst beginning low level works in the pavilion. Works continue to progress with the external...
-
Soil excavation works near the School of Management site
The University will be carrying out some enabling works starting on Monday 12 April in the grassed area to the East of the 8E building and to the North of the School of Management construction site. The enabling works include...
-
School of Management Project Update - March 2021
Externally the building continues to take shape with further elements of the façade installed. Internally the team continues to progress with the formation of multiple workspaces throughout the building. Externally progression has continued with the installation of the façade to...
-
School of Management Project Update - February 2021
Welcome to the monthly update focused on keeping you up to speed on progress being made at the University of Bath, School of Management project. The project continues to change significantly with the progression of works both externally and internally....
-
School of Management Project Update - January 2021
The team made good progress on multiple fronts on the run up to Christmas and have returned in the new year progressing with new work faces throughout. The external façade continues to take shape and over the period activity has...
-
School of Management Project Update - December 2020
We see the majority of glazing now installed on the elevations and commencement on multiple levels for the internal fit out. The external façade has changed drastically in the period as activity has continued all elevations. We now see most...