Impact of campus investment building projects

Keeping you updated on our current campus building projects

10 West: Project update

  , ,

📥  10 West

Progress to date

We are pleased to report the project is still on schedule

  • The concrete frame is now completed together with the atrium stairs which has allowed the crane to be removed from site.
  • As can be seen from the site, the majority of the windows are in and the larger glazing panels should be completed over the next couple of months.  A number of openings have been left to assist in material deliveries.
Most windows have been fitted

Most windows have been fitted

  • The roofing works are now well advanced and due for completion during October.  A separate temporary crane will be used to get the final materials to the roof. The aim is for the roof to be water tight in late October.
  • Internal partitioning works and M&E installations are progressing up to Level 4.
  • Raised access floors and plastering is well underway on all floors.

We are continuing to hold meetings with the end users of the building; members of the Department of Psychology have visited the site and they were very impressed with the progress.

10 West on schedule for completion

10 West on schedule for completion

Health & Safety

There have been no accidents and regular reviews continue to ensure a safe environment for those working on site and  pedestrians passing by.

Noise

Noise will continue at the same level as in previous months.

Did you know…?

We have over 5 miles of various types of pipework within the building, with 40 engineers working on it.

 

4 East South: Project update - August 2015

  , ,

📥  4 East South

Progress to date

The project is going well, and this month we have made good progress.

  • The reinforced concrete frame up to Level 4 on the West wing, and level 3 on the East has been completed. The West wing frame should be fully completed by the end of August.
  • Internal works have started on the data centre, and the fit out of the Mechanical and Electrical installation.
  • Work progresses at high level to form the first of the two double-height spaces (see below image). The pre-cast concrete floor is planned for delivery week commencing 10 August 2015.


Double Columns and Beams


Newly poured concrete of Level 4

 

Health & Safety

  • Bouygues-UK and the Bath site team are proud to announce that they have won the Gold ROSPA 2015 Award for Occupational Health and Safety.
  • Zero accidents on site; the team has received 100% score in the safety audit.

Did you know...?

This month we were very fortunate to receive a visit from students from across the country as part of the ‘Headstart’ programme, arranged with the University of Bath, to help young people gain an understanding of construction processes. It was an enjoyable and informative day - hopefully our visitors will be designing schemes of their own in the future!

The girls

The boys

 

10 West: Project update - August 2015

  , ,

📥  10 West

Progress to Date

Despite recent wet weather conditions, the project is still on schedule.

  • Construction of level 5 has been completed; work on level 6 is now underway and good progress is being made
  • Both north and south concrete stairs have been installed
  • With the completion of the concrete frame due within the next 4 weeks, ‘Crane 1’ has been removed in preparation
  • Internal partitions have started up to level 3, and first fix mechanical and electrics have progressed to level 2
  • Construction of the building’s façade continues:
    • Installation of the windows to the east block are complete to level 3
    • Elevator platforms have been added to the north and west scaffolding to allow façade works to proceed in these areas.
  • The atrium steel was installed as planned in readiness for level 6 roof and the installation of atrium glazing.

The Office of Policy and Planning are continuing to consult with the final users of the building to refine detailed requirements and furniture procurement.

Health and Safety
Extra measures and precautions remain in place relating to construction vehicles, and movements are monitored to ensure safety standards are maintained. These include measures such as banksmen who are helping vehicles to safely leave the site.

A secondary access to the site has been formed to help with deliveries and safe movement of vehicles.

There have been no injuries or accidents and the team are achieving exemplary levels of safety.

Noise
The noise levels will continue at the same level as they have been in the previous month.

Did you know…?
To stop rainwater from making its way down through the building and damaging the structure or causing problems, the construction team have used the existing service holes in the floor to install a temporary drainage system which guides water out of the construction site safely!

 

1 West Phase 3: Project Update July 2015

  , ,

📥  1West

Works to 1 West Phase 3 are moving along at a rapid pace and evidence of the new building is starting to emerge from the scaffold shroud that has been in place for the last few months.

Externally 50% of the new roof is complete with the temporary roof being removed at present. New windows have been installed to most of level 4 with level 3 underway. 1 west temporary roof removed

Internally the services and partition works are progressing in line with the programme with walls now being plastered and painted. 1 west level 2 interview rooms
New internal doors and glazed screens are due to start within the next four weeks.  1 west level 3

The project is scheduled for completion by 7 September 2015.

Midas Construction Ltd are pleased to have been instructed to carry out the re-roofing of the adjacent 3 West building with these works due to commence during July.

1 west forecast
Noise from the works will be unavoidable, however we hope the traffic light system above will assist.  It is not anticipated that the construction activity will create any more noise than the current ambient noise levels with the exception of the roof decking. Please also note that the dates above are a guide and likely to change as a result of unforeseen changes and site issues.

Scaffold & Temporary Roof

As can be seen the building is currently enclosed in a scaffold and temporary roof structure to allow the construction works to continue in the dry whilst the roof and windows have been removed. As works proceed these will be progressively removed to expose the new building. The site will be accessed from the level 1 underdeck to minimise contractor interaction with the student population. Site offices are in Brendon Court car park.

1 west level 4 terrace roof

Safety will always be paramount to all our operations on site.

Disruption to adjacent building users

We do not anticipate any major interface issues with the current use of 1West, Library and 3West however there will be times when works at the junctions with these buildings will require alterations and additional hoarding to allow the tie in to be completed. These will be timetabled and managed in conjunction with the University Estates team. Interface works will be segregated at all times ensuring that the safety of the building user is paramount at all times.

Pedestrian Movement at site entrance

Site delivery numbers will now increase, all vehicle movements will be strictly managed by Midas traffic marshal and by timing of deliveries around peak pedestrian movements times. Please take direction as required at site entrance gates from Traffic Marshals for your own safety.

 

 

4 East South: Project update - July 2015

  , ,

📥  4 East South

Progress to date

Main build

  • The concrete structure for level 1-2 has been completed with level 3 due to start in July.
  • Works have started on the internal fit out, with some corridors and plant rooms ready for the first fix electrical installation, due to take place in the next month.
  • Next week construction of the new data centre, which will be the hub for the campus, begins. This will take approximately 26 weeks to complete and it will be ready for testing early next year.
4 East South under construction

4ES - The concrete structure for level 1-2 has been completed with level 3 due to start soon

Energy Centre

  • The Energy Centre is complete and fully energised.
  • This building will be handed over to the University during July together with part of the access road.

Health & Safety

  • Zero accidents on site; the team has received 100% score in the safety audit.
  • Ongoing reviews are underway to optimise safe construction methods and improve risk management, including safety measures regarding working in high temperatures.

Environmental

  • 99.9% of site waste to date continues to be diverted from landfill.

Did you know...?

In July 2015, we have students from local schools visiting the site to gain an understanding of construction processes.

General queries can be addressed to estates-helpdesk@bath.ac.uk

Please also see http://www.bath.ac.uk/campus-investments/ and http://www.bath.ac.uk/estates/

 

10 West: Project update - July 2015

  , ,

📥  10 West

Progress to date

The project is on schedule and continues to benefit from the good weather conditions:

  • Construction of level 4 has been completed; work on level 5 is now underway and good progress is being made.
  • Internal partitions have commenced up to level 2 and first fix electrics have started on the ground floor.
  • Construction of the building’s façade is in progress and will continue for the next few months.
  • The western element steel frame and floors are completed and staircases will be completed in the next month.
  • The atrium steel will be installed in the next month encompassing a 18m steel member lift which will form the support to the atrium glazing. This work will be carried out first thing in the morning to prevent disruption.

The Office of Policy and Planning continues to consult with the final users of the building, the Department of Psychology, to refine detailed requirements and furniture procurement.

10 West build

The new 10 West building is on schedule

Health and Safety

Extra measures and precautions remain in place relating to construction vehicles and movements are monitored to ensure safety standards are maintained. These include measures such as banksmen who are helping vehicles to safely leave the site.

A secondary access to the site has been formed to assist in deliveries and safe movement of vehicles.

There have been no injuries or accidents and the team are achieving exemplary levels of safety.

Noise

The noise levels will continue at the same level as they have been in the previous month.

Did you know…?

There are daily logistics meetings about the cranes to make sure every slot is filled to maximise their effective use.

General queries can be addressed to estates-helpdesk@bath.ac.uk

Please also see http://www.bath.ac.uk/campus-investments/ and http://www.bath.ac.uk/estates/

 

Temporary closure of footpath from West car park to Medical Centre

  

📥  10 West

As part of the 10W project, new gas and data services need to be run from car park D (South of 2 South building) to the new 10W building.

The route involves excavating and laying new services along the footpath that connects the West car park to the Medical Centre, along the South edge of the lacrosse pitch and through car park D.

The works are expected to last for 8 to 9 weeks, starting on Monday 22 June from 10W progressing towards car park D.

  • The footpath that connects the West car park to the Medical Centre (highlighted in green on the map) will be closed for a 3 to 4 week period from this date.
  • The public footpath (highlighted in blue on the map) will remain open for the duration of the works.
  • An alternative route is available by joining the public footpath nearer to Quarry Road at the far end of the West car park (highlighted in magenta on the map).

10W-FOOTPATH-CLOSURE
Further footpath and parking closures may be required as the works progress. We will keep you informed on these pages.

 

1 West Phase 3: Project Update June 2015

📥  1West

Midas Construction Limited continue apace with the reconstruction and fit out.

Installation of the ductwork for ventilation and infrastructure for the electrical services is currently underway.

Works to replace the existing roof with a high performance insulated felt roof have started and will continue over the next seven weeks.

Internal partitioning is due to start soon to provide bespoke office, laboratory and general teaching spaces.

Replacement windows are due on site in early June and scaffolding will start to be struck later in June.

Works to refurbish the existing staircase will also be starting in the next month.

Level 5 roof deck

Level 5 roof deck

Level 2 ductwork

Level 2 ductwork

Potential disturbance

1-West-Capture-2
Noise from the works will be unavoidable, however we hope the traffic light system above will assist.  It is not anticipated that the construction activity will create any more noise than the current ambient noise levels with the exception of the roof decking. Please also note that the dates above are a guide and likely to change as a result of unforeseen changes and site issues.

We do not anticipate any major interface issues with the current use of 1West, Library and 3West however there will be times when works at the junctions with these buildings will require alterations and additional hoarding to allow the tie in to be completed. These will be timetabled and managed in conjunction with the University Estates team. Interface works will be segregated at all times ensuring that the safety of the building user is paramount at all times.

Scaffold and temporary roof

The building is currently enclosed in a scaffold and temporary roof structure to allow the construction works to continue in the dry whilst the roof and windows have been removed. As works proceed these will be progressively removed to expose the new building. The site will be accessed from the level 1 underdeck to minimise contractor interaction with the student population. Site offices are in Brendon Court car park.

Safety will always be paramount to all our operations on site.

Pedestrian movement at site entrance

Site delivery numbers will now increase with the refurbishment of the now empty building shell, all vehicle movements will be strictly managed by Midas traffic marshal and by timing of deliveries around peak pedestrian movements times. Please take direction as required at site entrance gates from Traffic Marshals for your own safety.

General queries should be issued to estates-helpdesk@bath.ac.uk.

Please also see the campus investments webpages.

 

10 West: Project Update - June 2015

📥  10 West

Progress to date

The project is on program and continues to benefit from the good weather conditions:

  • The construction of level 3 has been completed, level 4 is also making good progress.
  • The erection of the steel frame to the west block and atrium is now completed.
  • The facades are now commencing which will allow the internal trades to start work in the near future.
  • The insitu reinforced concrete feature atrium staircase is now in progress.

Ongoing reviews continue with the final users of the building, the Department of Psychology and the Office of Policy and Planning, refining detailed requirements and furniture procurement.

Health & Safety

Extra measures and precautions remain in place around the site when construction vehicles leave and are being monitored to ensure safety. These include measures such as banksmen who are helping vehicles to safely leave the site.

To date there have been no injuries or accidents, the team continue to achieve exemplary levels of safety.

Noise

The noise levels will continue to the same level as they have been in the previous month.

Did you know?...

This project is one of the projects being showcased by the Institute of Civil Engineers as a major project contributing to the local infrastructure, economy and employment.

General queries can be addressed to Estates Helpdesk

Please also see Campus investments webpages and Estates webpages

IMG_1086

10 West progress to date