Impact of campus investment building projects

Keeping you updated on our current campus building projects

10 West: Project Update

  , ,

📥  10 West

The project is making good progress and remains on schedule despite recent stormy weather conditions.

  • The North Atrium curtain wall (a weather proof outer layer of the building) has been glazed and works are progressing internally. The scaffolding will be removed from the atrium by the end of the month.
  • Services have been connected, allowing commissioning of water and electricity to start.
  • The installation of vinyl and whiterock in all toilet/shower facilities is nearing completion. Sanitary equipment is also being fitted.
  • Final decorations have begun on all levels and carpet laying has commenced on Level 3.
  • Hard landscaping is progressing well around the building.
  • New smaller site accommodation is in place and the main site offices will be removed in March.

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

 

4 East South: Project Update

  , ,

📥  4 East South

The project has made good progress despite recent stormy weather conditions.

  • Large segments of the West core are nearing completion which means work can now move on to the East core.
  • Concrete works in the West core are complete.
  • The installation of electrical trunking in the West core has been completed, providing power to audio visual equipment and plug sockets.
  • Internal doors and glass partitioning have been installed.
  • Suspended ceiling systems in the West core have been installed on Levels 2-5, and preparation has begun on Level 5.
  • Worktops and cabinets are currently being installed in kitchen areas.
  • The installation of Reglit feature glass has begun on the North elevation. This needs dry weather as each element must be prepared to allow the glass to perform to its maximum efficiency. The site team have a covered preparation zone so in a dry spell the glass can be installed quicky.
  • The final section of screeding on Level 6 is underway. Once complete the underfloor heating will be installed.

Health & Safety

One minor accident occurred in February, a small flesh wound on a finger caused by a scaffold pole.

 

10 West: Project Update

  , ,

📥  10 West

10 w feb

The project remains on schedule despite the winter weather conditions:

  • Work on the building’s façade is progressing well and the installation of the final composite tiles is nearly finished.
  • Internal works continue to make good progress with the installation of glazed decorative screens.
  • Floor finishings to wet areas are nearly finished.
  • Final fix carpentry is nearly finished.
  • Final finishings to the main entrance and Atrium staircase have begun.
  • Installation of glass balustrades in the Atrium has been completed.
  • Access scaffolding in the atrium is being removed to allow the final works on the floor to begin.
  • Structural work on the main entrance and podium walkway has been completed.
  • Installation of the steel framed walkway to the Podium will begin in early February.
  • Landscaping work has begun and the connection to the 8 West ramp is nearly finished.
  • The site team’s office will be removed in March so that major landscaping works can begin, and a smaller temporary office will be installed.

 

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

Did you know…

Since the start of the construction project the site team has used over 207,200 tea bags, 22.5kg of coffee and 171kg of sugar.

 

4 East South: Project Update

  , ,

📥  4 East South

January has seen the project move forward considerably:

  • Large areas of the building are now boarded and plastered.
  • Raised access flooring has been laid up to level 5 in the West section.
  • The East exhibition space has been fully boarded, plastered and first coated.
  • Underfloor heating systems have been installed.
  • External feature windows on the North elevation have been installed.
  • Windows across the full South Elevation have been installed.
  • Dry lining can now continue without the fear of water damage.
  • Installation of cladding panels has started.
  • The Energy Centre external path has been completed. The pathway has been constructed at a 1 in 20 gradient with resting stations for wheelchair access.

Health & Safety

There have been no injuries or accidents on site.

Did you know...?

Bouygues currently employ two Masters of Civil and Structural Engineering on the 4ES project, showing the opportunities for students to progress into industry.

 

 

4 East South: Project Update

  , ,

📥  4 East South

The project has made good progress during December despite a halt in construction over the Christmas period and the recent bad weather conditions:

  • Screeding (levelled concrete flooring) has been completed on level 4.
  • The underfloor heating system has been installed.
  • Installation of paving slabs on the West core roof has been completed.
  • Over 90% of the building’s windows have been installed.
  • East core has been fully insulated.
  • Installation of radiators has begun on Levels 2 and 3 in the West core.
South elevation

South elevation

Internal

Internal progress

Health & Safety

There have been no injuries or accidents on site.

The site has achieved a 98% score in the recent health and safety compliance audit. The team has never scored lower than 97%.

Did you know...?

To date over 170 tons of reinforced steel has been used in the structure, the equivalent weight of a fully grown Blue Whale.

 

10 West: Project Update

  , ,

📥  10 West

The project has made good progress and remains on schedule, despite the halt in construction over the Christmas period:

  • Work on the façade continues on all elevations despite delays due to the recent high winds and heavy rainfall.
  • Screeding (levelled concrete flooring) has now been completed on all levels.
  • Installation of pre-cast concrete planks and precast stairs has been finished in the North elevation.
  • Structural topping (a layer of concrete and wire mesh on top of floor slabs) is now complete throughout the building.
  • Raised access floors on Level 5 are in the final stage.
  • Fitting of balustrade glass within the Atrium has made good progress.
  • Fitting of internal glass partition screens has progressed to Level 4.
  • Mechanical, electrical and second fix carpentry has made excellent progress on all levels
  • Work on the lift infrastructure is now 80% complete.
  • Internal plastering is nearing completion with work remaining on Levels 0 and 1.
  • Installation of White Rock (hygienic wall cladding) has begun in toilets and kitchens.

 

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

 

 

4 East South: Project update

  ,

📥  4 East South

Despite the recent windy conditions and heavy rainfall progress has been good.

  • The building’s West core has received a weather proof coating.
  • All windows have been installed on the West core.
  • The West core is scheduled to be completely water tight by early December.
  • Construction of the parapet walls on the East core has begun.
  • In December the parapets will be covered with an asphalt layer.
  • Internal mechanical and electrical works have begun.

Health & Safety

There have been no injuries or accidents on site.

The site has achieved a 98% score in the recent health and safety compliance audit. The team has never scored lower than 97%.

Did you know...?

The site team recently took part in the Chartered Institute of Building’s charity quiz and raised £2004 for the Wallace and Gromit appeal.

 

 

10 West: Project Update

  ,

📥  10 West

The project has made good progress and remains on schedule, despite recent weather conditions.

  • Work continues on the Podium to prepare for the installation of concrete planks on 7 December.
  • Internal work has now commenced on Level 5, coinciding with the installation of lifts.
  • Final work has begun on the building’s façades, including external rendering, fitting glass panes and cosmetic finishes.

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

Installation of cosmetic finishes on the building’s southern façade

Installation of cosmetic finishes on the building’s southern façade

 

10 West: Project update

  , ,

📥  10 West

Progress to date

The project remains on schedule and the team are well prepared for difficult winter weather conditions.

  • Excellent progress has been made on the façades on all elevations to prepare for installation of final finishings.
  • Work on the roof has nearly finished.
  • Preparation for the installation of photovoltaic panels has begun.
  • Internal works throughout the building are progressing well, and the final joinery stage has begun.
  • Installation of glazed screens will begin soon.
  • Final works within the Atrium and on the feature stairwell have started and should be complete by late December 2015

Health and Safety

There have been no injuries or accidents on site, reviews continue to ensure a safe environment for the site team and pedestrians.

Noise

The noise levels will continue to be the same as previous months.

Did you know…?

On 22 October 2015 the Vice-Chancellor, Professor Dame Glynis Breakwell, together with representatives from the University’s Council and Vinci Construction attended a Topping Out ceremony. Topping Out ceremonies are held when a new building reaches its highest point. Traditionally the ceremony is conducted to thank workers for their efforts and to honour their safety.

10W-topout-3

 

4 East South: Project update

  , ,

📥  4 East South

Progress to date

The site team have made excellent progress during October and remain on schedule.

  • The roof has been completed and a weatherproofing will begin in November.
  • Once the roof has been made weather tight internal works will commence.
  • The erection of the West core steel frame is nearing completion.
  • Installation of reinforced concrete planks has been completed on the East core, Level 7.
  • The installation of windows on the south elevation’s façade has commenced.
  • Internal partitioning and plumbing on levels 1 to 5 which is going well.
4es-nov-small

Health & Safety

There have been no injuries or accidents on site.

The site team has achieved a ‘Beyond Compliance Award’ from the Considerate Constructors Scheme. This award shows the team’s dedication to health and safety standards, as well as their commitment to customer services to both staff and neighbours.

Did you know...?

The site team has used approximately 1100 cubic meters of concrete and 200 tons of re-enforced steel on on the project, which is the same amount that was used for NASA’s initial Space Launch System.